April 28 2025

Light Poles Installed & Punch List of Final Items Completed

April 01 → December 13 2024

Construction

December 13 2024

Retaining Wall on Grandview Ave. Built

November 29 2024

Phase 3 Milling and Paving

November 2024

Concrete Curbs Poured

November 2024

Seeding and Landscaping/Restoration

November 01 2024

Private Water Line Transfers

October 2024

Phase 1 Bumpouts Installed on South Side of First Ave.

October 2024

Phase 2 Bumpouts Installed on North Side of First Ave.

October 25 2024

Community Meeting

If you were unable to attend the meeting, you may watch the meeting in its entirety at https://youtu.be/SOcxRHTspk4.

July 15 2024

Storm Sewers Installation

June 10 2024

Sanitary Sewer Work from Oxley Road to Williard Ave.

Work on the First Avenue reconstruction project will ramp up starting this week. Pipes have been delivered for utility work as water and sewer will be the first phase. To facilitate the installation of new sewer infrastructure, a pump will be on site to redirect sewer flow while new pipes are installed. The pump hose will extend across the intersection of First & Oxley, requiring a temporary plate in the intersection. The lights will be switched to a temporary red flash for motorist safety while the pump is in place and return to normal operation once the pump is removed.

June 03 2024

Waterline Work Grandview Ave. to Virginia Ave.

January → March 2024

Bidding

February 06 2024

Public Meeting

5p @ the Grandview Center (Parks & Recreation Building), 1515 Goodale Boulevard

March → December 2023

Planning and Engineering